It’s been a busy time for our site team at Asebu Model Kindergarten and the school is really starting to take shape.

Some of the key activities achieved this since our last update in May include:

  • The casting of the concrete for the upper ring beam which supports the roof. You can see in the images the metal truss shoes protruding from the beam, which will be used to secure the roof trusses.
  • Concrete works for the main classroom block have been completed, including the ground slab.
  • Pathways for the main classroom block are complete.
  • The roof trusses which are prefabricated have been fitted to the ring beam and are now ready for the purlins and roofing sheet.

Watch this space for more from our Building Better Schools programme…