ABUESI UPDATES:

  1. Roofing sheet installed at 100%.
  2. Ceiling boards and sound/heat insulation material installed at 100%.
  3. Two OTAs, latrine and kitchen roofing installed.
  4. Ramp and stairs concrete works complete at 80%.
  5. Walkways linking various units complete at 100%.
  6. Cladding works to main building still in progress and at 60% complete.
  7. Installation of doors and window openings complete at 60%.
  8. Tarrazzo work in progress and complete at 30%.
  9. Fence wall complete at 60%.
  10. Playground and Assembly kerb complete at 90%.

 

OUTSTANDING WORKS :

  1. cladding works to latrine and kitchen framework.
  2. Blockworks on top of latrine and kitchen ground beams.
  3. Windows and Doors installation.
  4. Installation of designed blocks and balustrade to fence wall, ramp and stairs areas.
  5. Painting of main building, kerbs, latrine and kitchen Blockwork, fence wall columns.
  6. Tyrolienne finish to part of the fence wall.
  7. Playground toys
  8. Sea/river sand to fill two OTAs