ABUESI UPDATES:
- Roofing sheet installed at 100%.
- Ceiling boards and sound/heat insulation material installed at 100%.
- Two OTAs, latrine and kitchen roofing installed.
- Ramp and stairs concrete works complete at 80%.
- Walkways linking various units complete at 100%.
- Cladding works to main building still in progress and at 60% complete.
- Installation of doors and window openings complete at 60%.
- Tarrazzo work in progress and complete at 30%.
- Fence wall complete at 60%.
- Playground and Assembly kerb complete at 90%.
OUTSTANDING WORKS :
- cladding works to latrine and kitchen framework.
- Blockworks on top of latrine and kitchen ground beams.
- Windows and Doors installation.
- Installation of designed blocks and balustrade to fence wall, ramp and stairs areas.
- Painting of main building, kerbs, latrine and kitchen Blockwork, fence wall columns.
- Tyrolienne finish to part of the fence wall.
- Playground toys
- Sea/river sand to fill two OTAs