Great progress has been made on the Primary block over the last few weeks. After the concrete pour for the block’s foundation was completed the slab base for the inner perimeter was prepared and filled with hardcore materials.

All of the column rebars were fixed which allowed for each of the 17 columns for the Primary block to be cast using plastic formwork.

Work on the Kindergarten block has also continued at an excellent pace with all of the ring beam bars for the block now fixed.

On top of this, 500 sandcrete blocks have been moulded ready for use on the Primary and Kindergarten blocks.

The classrooms are really starting to come to life now…check back here soon for some more exciting updates!