There has been some fantastic progress on site at Akwidaa Model Kindergarten School over the last month, despite the heavy rains.

  • Wooden form work has been removed from the foundation ground beam.
  • The classroom block slab has been built up with hardcore and sand, in preparation for the Damp Proof Membrane and pouring of the concrete floor slab.
  • The Damp Proof Membrane has been laid and classroom slab has now been cast.
  • The column and upper ring beam steel rebars have been erected ready for the completion of concrete works.
  • Pathways for the school are underway.
  • Column formwork was used and all 15 columns have been cast.

Great work team!