Our site team working at Ahobre Early Years Complex have had a productive few weeks.

On the kindergarten block the following tasks have been completed:

  • Spreading of 20mm thick layer of sand on the filled hardcore floor.
  • The Damp Proof Membrane has been laid.
  • The tying of the slab mesh.

On the primary block the following activities have been completed:

  • The fixing of foundation formwork.
  • Fixing of the foundation rebar.
  • The concrete pour for foundation.

Our Trustee and Founder, Aubrey Malcolm-Green, also visited the site with Lisa Rose, our new Construction Programme Manager. Watch this space for more exciting staff updates from Ghana!