There has been some great progress on site at Ahobre Early Years Complex, and the team are on schedule.

Eleven artisans were recruited in February to work on the construction project, with six of them coming from the local community.

The fabrication of foundation steel rebar cages for both the kindergarten and primary classroom blocks has been completed.

Truss fabrication for the roof of the primary block has started.

The foundation formworks for the kindergarten block were prepared and fixed, ready for the placement of the foundation rebar cages. Once these were in place the concrete for the foundations could be poured.

The first project milestone was completed ahead of schedule – the casting and curing of the
foundation for the kindergarten classroom block.