It has been a great couple of weeks on site at Holy Child Kindergarten Centre of Excellence.
The planting areas now have grasses in place and all concrete work has been completed on the third classroom (KGB2).
The roof trusses are being fabricated onsite and have been erected on one of the classrooms already – KGB1.
The poly tank platforms are an integral part of the rainwater harvesting system and have been built for two of the three classrooms, KGA and KGB1.
- Grasses planted
- Concrete work finished on KGB2
- Assembling roof trusses
- Poly tank platform construction
- Poly tank platform